Walermare Stage One Sold Out

Walermare Highfields, Stage One Sold Out - February 2026

We’re excited to share the latest on-site progress at Walermare. Civil construction is tracking well, with bulk earthworks now complete and key infrastructure works advancing across the estate. Progress to Date

  • Cut to fill earthworks completed: 21,786 m³
  • Subgrade passed Council inspection: 228 m (Road 1) and 150 m (Road 3)
  • Subbase constructed: 1,583 t (2.3 Gravel)
  • Kerb constructed: 833 m
  • Stormwater laid: 1,038 m
  • Stormwater structures constructed: 24

Next Steps Water installation is commencing this week, marking the start of the next key phase of infrastructure delivery. We look forward to keeping you updated as Walermare continues to take shape and moves closer to welcoming its future residents.